Station Quarter, Telford

DemolitionRemediation
Project Value £1,500,000.00
Project Programme Period 30 Weeks
Type of works Demolition, Remediation and Earthworks

Introduction

Station Quarter, the gateway from Telford Central train station through to Telford’s town centre, has been dominated for some time by cleared, brownfield sites, once occupied by unsustainable and outdated office buildings.

A large-scale enabling works package was completed to prepare the site for development.

Works Description

The remediation approach focused on the removal of relic obstruction and deleterious material from the made ground and returning the site back to a developable platform.

The approved remediation strategies targeted the significant reduction in key contaminant concentrations utilizing a progressive turnover and reclamation strategy to identify and excavate ground areas that were heavily impacted.